IV. RECOMMENDATION FOR WIND TURBINE PROJECT
Administration provided an overview of the wind turbine project. The proposed project calls for installation of a Northwind 100 kW wind turbine and a 15 kW wind turbine on the southeast corner of the Wausau East High School campus adjacent to the Zastrow Wetland Education Area. The Northwind turbine, rated at 100 kW, has a rotor diameter of 20 meters and a total height of approximately 157 feet. The 15 kW turbine has a rotor diameter of 17 meters and a total height of 152 feet.
The cost of the project is approximately $574,566. Funding sources for the project are the Walter Alexander Foundation ($400,000), Focus on Energy grants ($129,000), and District funds ($50,000). Outside financial sources are expected for the solar panels ($24,000). Other financial sources may become available for the project.
Estimated annual revenues were discussed. The annual energy output of the two turbines is 120,602 kW with an estimated annual revenue of $16,542. The Wausau School District will receive a return on their investment ($50,000) in approximately four years.
No comments:
Post a Comment